Aalo Atomics plans a $25 million renovation of a 204,350-square-foot Georgetown warehouse into reactor lab and production space, with completion set for 2028.

Quick Answer: Austin-based nuclear reactor developer Aalo Atomics plans a $25 million renovation of a 204,350-square-foot warehouse in Georgetown into lab, machine shop and production space. A state filing lists a November 15, 2026, start and a January 30, 2028, completion. The site would support Aalo’s plan to mass-produce small reactor “pods” for data centers.

What is Aalo Atomics building in Georgetown?

A project registration filed August 31, 2026, with the Texas Department of Licensing and Regulation (TDLR) describes the renovation of an existing one-story warehouse “to provide lab, machine shop and production floor space for Aalo Atomics advanced manufacturing.” The project is registered as Crosspoint Building 1 at 4813 North Interstate 35 in Georgetown, in Williamson County.

ConnectCRE, citing Community Impact, reported in September that the project was expected to break ground in November and be completed by early 2028, matching the dates in the state filing.

Project snapshot from the state filing

Item Detail
Project name Crosspoint Building 1 – Renovation
Address 4813 North Interstate 35, Georgetown, TX 78633 (Williamson County)
Registered August 31, 2026
Estimated cost $25,000,000
Building size 204,350 square feet, one story
Scope Lab, machine shop and production floor space for Aalo Atomics
Scheduled start November 15, 2026
Scheduled completion January 30, 2028
Property owner DRI JS Georgetown I, LLC (Dallas)
Design firm Corgan
Funding Privately funded, on private land for private use

The filing does not list a job count. Some trade roundups have cited hiring and square footage figures that do not match the state record, so this article relies on the TDLR registration for the building’s size and cost.

Who is Aalo Atomics?

Aalo was founded in 2023 and is led by CEO Matt Loszak, with Yasir Arafat as president and chief technology officer. In August 2024, the company opened a 40,000-square-foot factory and headquarters between downtown Austin and the airport, where it said it would build its experimental reactor and eventually manufacture its core product.

In August 2025, TechCrunch reported that Aalo raised $100 million in a Series B round led by Valor Equity Partners, with participants including Hitachi Ventures, NRG Energy and Tishman Speyer. That same month, according to the American Nuclear Society, Aalo broke ground on its Aalo-X facility at Idaho National Laboratory.

What reactors does Aalo make?

The American Nuclear Society described Aalo’s core design in March 2026 as a 10-megawatt-electric, low-enriched-uranium-fueled, sodium-cooled reactor, with the Aalo-X as its first full-scale demonstration. TechCrunch described an “Aalo Pod” as five Aalo-1 reactors feeding a single turbine to produce 50 megawatts of electricity, aimed at powering data centers.

How far along is Aalo’s reactor program?

Aalo is part of the U.S. Department of Energy’s Reactor Pilot Program. The timeline below draws on the American Nuclear Society, ConnectCRE and Aalo’s own news listings.

Date Milestone
August 2024 Opens 40,000-square-foot Austin factory and headquarters
August 2025 $100 million Series B; Aalo-X groundbreaking at Idaho National Laboratory
January 2026 Final design review with DOE and NRC reviewers completed
March 4, 2026 DOE approves Preliminary Documented Safety Analysis
May 5, 2026 DOE-Idaho approves safety analysis for Aalo-X critical test reactor
July 4, 2026 Aalo announces criticality, the Reactor Pilot Program target date
August 31, 2026 Georgetown renovation registered with TDLR
November 15, 2026 Scheduled Georgetown construction start
January 30, 2028 Scheduled Georgetown completion

ConnectCRE reported that Aalo’s critical test reactor achieved a self-sustaining nuclear reaction and was built in less than eight months. The American Nuclear Society reported that Baker Hughes is to deliver a 10-megawatt turbine for the Aalo-X by the end of 2026.

What comes after the Aalo-X?

Aalo’s 2026 plan, published in February, said the full Aalo-X would not be completed until the end of 2026. In March, Arafat told the American Nuclear Society that the company was gearing up to submit its first commercial license application to the Nuclear Regulatory Commission this year, and he described a goal of having 1 gigawatt online by the end of the decade.

Is Georgetown the “GigaWatt Factory”?

Not according to anything on the public record. In March, Arafat told the American Nuclear Society that Aalo planned a full-scale, 1-million-square-foot “GigaWatt Factory” to be online by 2028, capable of making at least 100 reactors a year at maximum capacity. The Georgetown building is about one-fifth that size, and none of the sources reviewed connects the two. Georgetown appears to be a step between the Austin headquarters and any larger plant.

Brian’s Take

I like that this project shows up first in a state building filing rather than a splashy ribbon-cutting. A $25 million renovation of an existing warehouse, privately funded, with a start date and a finish date on record, is the kind of measured step that tells you a company is moving from prototype toward production.

The sequence matters. Aalo raised $100 million, built a test reactor in Idaho, reported reaching criticality on its July 4 target and only then committed to more manufacturing space in Williamson County. That is a better order of operations than building the factory first and hoping the technology catches up.

What I would want to see next is the hiring number, which the filing does not give, and some evidence that customers are signing up for the 50-megawatt pods. The Georgetown space is a bet that the demand from data centers is real. Texas wins either way on the construction work, but the long-term payoff depends on orders.

Frequently Asked Questions

How much is Aalo Atomics spending in Georgetown?

The state filing lists an estimated cost of $25 million.

Where is the Georgetown facility?

At 4813 North Interstate 35 in Georgetown, in a building registered as Crosspoint Building 1.

When will it be finished?

The TDLR filing lists a January 30, 2028, completion date.

Will nuclear fuel be handled at the Georgetown site?

The filing describes lab, machine shop and production space and does not mention fuel. Aalo’s Aalo-X reactor facility is located at Idaho National Laboratory.

How many jobs will the facility create?

No job count appears in the state filing or the company materials reviewed.

Sources and Further Reading

  1. TDLR Architectural Barriers Project TABS2026029277, Crosspoint Building 1 – Renovation, Texas Department of Licensing and Regulation
  2. Mini-Nuclear Power Plant Maker Building Georgetown Factory, ConnectCRE
  3. Nuclear power manufacturer to open $25 million facility in Georgetown, Williamson County Sun
  4. Aalo Atomics discusses the road ahead, American Nuclear Society
  5. Aalo Opens 40k Sqft Factory HQ in Austin, Texas, Aalo Atomics
  6. Aalo Atomics raises $100M to build a microreactor and data center together, TechCrunch